Pumping Station Problem & Solution
Installation of a Raw Pumping Station for a New Classroom at a Primary School
Project Overview
Many educational institutions constantly evolve to accommodate the needs of its growing student population. Recently, a Local Primary School built a new classroom to cater to increasing enrollment. To support this expansion, the school required a reliable solution for managing wastewater, essential for keeping the facility safe, functional, and compliant with regulations. We were tasked with the installation of a raw pumping station to serve the new classroom.
Challenge
The primary challenge was timing. Schools are busy environments, and any work during term time could disrupt daily activities, create safety risks, and cause significant inconvenience for students, staff, and parents. The key requirement was to complete the installation swiftly and discreetly during the summer holidays, ensuring everything was in place and fully operational before the new school year.
Our Approach
Understanding the need for minimal disruption, we scheduled the entire project to coincide with the school’s summer break. This allowed us to carry out the installation without interference, ensuring the safety and convenience of everyone on site.
The project involved:
- Assessment and Planning: A thorough site inspection to determine the optimal placement for the raw pumping station.
- Equipment Installation: The installation of the raw pumping station, which included connecting it to the school’s existing infrastructure, ensuring smooth wastewater management.
- Testing and Commissioning: After installation, we set the system up and tested the system to enable us to supply a commissioning certification, allowing final signoff by building control.
Results
The project was completed on time before the new term began, and within budget. When the children and staff returned after the summer holidays, they were greeted by a fully functional and upgraded facility without even noticing our presence.
Impact
- Improved Infrastructure: The new raw pumping station ensures the efficient management of wastewater from the new classroom, supporting the health and safety of the students and staff.
- No Disruption: By carefully timing our work during the summer holidays, the school experienced zero disruption, allowing them to focus on the upcoming academic year.
- Future-Proofing: The installation of this essential infrastructure upgrade ensures that the school is prepared for future expansions and maintains compliance with local regulations.
Conclusion
Our team completed the installation with precision and care, reflecting our commitment to delivering high-quality services with minimal disruption. The school can now confidently move forward with its new classroom, supported by a reliable wastewater system designed to meet the needs of its growing community.
When parents and children returned, they didn’t notice we had been there—but they’ll benefit from our essential upgrade that helps keep their school running smoothly.
If you are a business that needs a new sewage treatment solution, but can’t afford the disruption during peak periods, or due to the nature of your operations, please get in contact.
For further assistance and advice, contact us on 01255 853890 | enquiries@mantair.com – or by filling out the form on our contact us page.